Minnesota Journeyman PrepLicense, exam and code, in one place Start the free practice testPractice exam

Checked against primary sources 2026-09-07

The edition for the job

Which NEC Edition Minnesota Uses for Work Right Now

Two different questions get the same answer in most states and different answers here. The edition for a permit and the edition for an examination moved on different days in Minnesota, and the published rule text has not caught up with either.

Test yourself: thirty free questions, timed

On this page
  1. The answer for work
  2. The rule it lives in
  3. The published text still says 2023
  4. What to do with that
  5. Who you file the permit with
  6. Why Minnesota tracks the current edition
  7. Questions people ask
  8. What this page cites

The answer for work

DLI states it in three sentences on its codes and standards page. The Board of Electricity has adopted the 2026 National Electrical Code with an effective date of Aug. 17, 2026. Electrical permits filed before Aug. 17, 2026 must comply with the 2023 NEC. Electrical permits filed on or after Aug. 17, 2026 must comply with the 2026 NEC.

So the permit date decides the edition, not the date the work is done. A job permitted in July 2026 is a 2023 job even if you are wiring it now.

The examination is a separate date. That is September 8, 2026, and it is covered on the exam edition page.

The rule it lives in

Minnesota's electrical code is Minnesota Rules chapter 1315, titled Electrical Code, under the Board of Electricity. Part 1315.0200, subpart 1 says the chapter shall be known and cited as the Minnesota Electrical Code.

The chapter is short. Only 1315.0200 is active. Parts 1315.0300, 1315.0500 and 1315.0600 are marked repealed by amendment and 1315.0400 is marked repealed.

DLI describes what the chapter does as adopting a national standard for the installation of electrical wiring, apparatus and equipment for electric light, heat, power, technology circuits and systems, and alarm and communication systems.

The published text still says 2023

This is the part nobody else prints, so read it carefully.

As read on September 7, 2026, the Revisor of Statutes page for 1315.0200 still carries the pre amendment text. Subpart 1a as published requires compliance with the 2023 edition of the National Electrical Code as approved by the American National Standards Institute, ANSI/NFPA 70-2023. The page is stamped Published Electronically: July 20, 2023 and its history line ends 45 SR 426; 47 SR 1185. The 2026 edition does not appear on it anywhere.

Against that, DLI's rulemaking docket says the rules were filed with the Secretary of State on July 20, 2026 and will be effective as of Aug. 17, 2026, and the rule draft shows 2023 struck and 2026 inserted, with ANSI/NFPA 70-2023 struck and 70-2026 inserted.

Both are official Minnesota sources and we do not resolve it here. The likely explanation is publication lag on the Revisor's site, but nothing states that and we are not going to assert it. Read the amendments page for the full record.

What to do with that

Work to the 2026 edition on any permit filed on or after August 17, 2026, because that is what DLI and your inspector will apply.

If a dispute ever turns on the published rule text rather than on DLI's statement, get the rule draft and the docket page in front of whoever is deciding, and ask DLI rules staff. The contact on the docket is Krystle Conley, dli.rules@state.mn.us, 651-284-5006.

Check the Revisor page again yourself before you rely on any of this. It may have been republished since we read it.

Who you file the permit with

Minnesota splits electrical permits between the state and local authorities. DLI tells contractors that if the authority having jurisdiction column lists State, file the permit with DLI, and if the column shows Local, contact the local city or township.

Permits and inspections run through the DLI iMS portal, and DLI publishes inspector directories, an inspector lookup, a page on requesting an inspection and a remote virtual inspection service. Homeowners have their own permit page.

The edition question does not change by city. Minneapolis runs its own electrical inspection program, Saint Paul issues its own electrical permits, and Duluth sends electrical permits to the state, but all three sit on the same Minnesota Electrical Code.

Why Minnesota tracks the current edition

Because the statute tells the board to. Minnesota Statutes 326B.32, subdivision 2 directs the Board of Electricity to adopt the Minnesota Electrical Code, which must be the most current edition of the National Electrical Code.

That is why Minnesota is on the 2026 edition while several states are still working through the 2023 one, and it is why a Minnesota amendment set is a rarity rather than a routine.

Questions people ask

Which NEC edition does Minnesota use?

The 2026 edition, for electrical permits filed on or after August 17, 2026. DLI states that permits filed before that date must comply with the 2023 NEC.

Does the permit date or the work date decide the edition?

The permit date. DLI words it as permits filed before August 17, 2026 complying with the 2023 NEC and permits filed on or after that date complying with the 2026 NEC.

Why does the Minnesota rule still say 2023?

As read on September 7, 2026 the Revisor of Statutes text of Minnesota Rules 1315.0200, subpart 1a still incorporates the 2023 edition and carries a July 20, 2023 publication stamp, while DLI says the amended rule was filed on July 20, 2026 and took effect August 17, 2026. We print both and do not resolve it.

Where is Minnesota electrical code adopted?

In Minnesota Rules chapter 1315, part 1315.0200. Subpart 1 says the chapter shall be known and cited as the Minnesota Electrical Code, and it is the only active part left in the chapter.

Do Minnesota cities use a different code edition?

No city adopts its own electrical code edition. Cities handle permits and inspections, and DLI tells contractors to file with the state or the local authority depending on which is listed in the authority having jurisdiction column.

Why is Minnesota on a newer edition than my neighbouring state?

Minnesota Statutes 326B.32, subdivision 2 directs the Board of Electricity to adopt a code that must be the most current edition of the National Electrical Code.

Put it to the test

Thirty free questions, timed, with the working shown

Every miss comes back with the arithmetic worked out and the code section named, so you learn the trap and not just the answer. No account.

All questions here are original. They are not actual exam questions, and no question bank can promise you a pass.

What this page cites

If your notes still say 2023

The 2023 to 2026 section crosswalk maps every section that moved, both directions, $29 once.

NEC and National Electrical Code are registered trademarks of the National Fire Protection Association.

Trojan Digital Marketing is an independent company. We are not affiliated with, endorsed by, or sponsored by NFPA, the Minnesota Department of Labor and Industry, the Department of Labor and Industry, or any licensing authority, school or union.

The Minnesota examinations are open book on a book the department hands you. DLI provides the National Electrical Code in soft cover with no tabs or other aids, allows a laws and rules booklet and a basic calculator, and allows no other materials or electronic devices in the building. The questions follow the 2026 edition from 8 September 2026, and 17 August 2026 is the permit date rather than the exam date.

All practice questions are original. They are not actual exam questions.

Built and maintained by Jeff Clerisier, Trojan Digital Marketing.

Free, weekly

One exam question a week, worked all the way through

One original question in the Minnesota style, the arithmetic worked, the code section named, and a short note whenever a Minnesota licensing or code rule moves. Unsubscribe in one click.